Project / Application & fabrication
United Arab Emirates / ship-repair blankets
A ship-repair contractor needed modular blankets with consistent fixing positions. A pilot fit check resolved the eyelet drawing, while bulk release remained dependent on the site's documentation and schedule.
The customer and requirement
The customer is a UAE ship-repair contractor preparing a planned maintenance shutdown. The contractor purchases and installs the articles, while the shipyard's safety team controls acceptance for use in the work area.
The project called for blankets around a temporary hot-work zone, with consistent finished sizes, fixing positions and piece labels. Delivery packs needed to follow the layout of the work areas.

Material appearance reference
Material and specification review
A vermiculite-coated fiberglass blanket was considered as a material candidate. Suitability for the expected exposure and the site's permit requirements required separate review before any hot-work use.
| Requirement | Project detail |
|---|---|
| Candidate construction | Vermiculite-coated fiberglass with sewn edges; assembly subject to review |
| Proposed finished size | 2,000 × 2,000 mm |
| Eyelet layout | 500 mm nominal spacing with corner offsets defined on the approved drawing |
| Pilot and project forecast | 10 pilot pieces; 120 pieces in the project forecast |
| Labels and packing | Piece ID, drawing revision and work-area packing list |
| Use approval | Protective performance and site release require separate evidence |
Purchasing plan
The contractor planned around a six-week shutdown preparation window. The 120-piece quantity was a project forecast, with replacement needs to be assessed during later maintenance. No recurring purchasing interval was established.
Sample review
Ten pilot articles were prepared for a fit check without hot-work exposure. The team checked finished dimensions and fixing access against the installation drawing, keeping this review separate from any exposure evaluation or site release.
Resolving the detail
The buyer and sewing team initially measured the 500 mm eyelet spacing from different datum points. Bulk cutting was paused while corner offsets were added and drawing revision B was approved.
Project outcome
The corrected pilot met the dimensional review. Bulk release stayed on hold pending site documentation and the final schedule; the fit check did not establish fire performance or approval for hot-work use.
Next step
Close the site's evidence requirements and confirm the shutdown schedule before releasing the bulk fabrication.